Planning updates – Lincoln Court and Lowfields

  • MUGA

    We understand that the Foxwood Residents Association have formally objected to the Councils plans to “replace” the children’s all-weather games area on Kingsway. The objection stems from the Councils proposal to build “fitness equipment” on Chesneys Field during the summer. The Association points out that no consultation has taken place over this proposal which could intensify the use of what is Public Open Space. When a similar idea was mooted 2 years ago, the preferred site for a fitness track was judged to be the Thanet Road Sports Area. The Association have suggested that the Council seek a partnership with the Acorn Rugby Club which could see a new 3G games area provided. Sport England have also objected to the Council’s plans

  • The Yorspace proposals for the Lowfields site have been criticised by the local Drainage Board. They are asking for further details of how surface water runoff will be handled. They point out the fact that – for the whole site –  water run off is likely to be more severe than occurs from the existing greenfield use. There are already some problems with flooding in the gardens of some properties in the Green Lane and Tudor Road area.
  • Separately the Lowfields Residents Group has objected to plans which would see the number of off street parking spaces reduced near 108 Tudor Road. They are also concerned about the traffic implications of building a new access road onto the Lowfields site

NB. The contract for “enabling works” at Lowfields was awarded to NMCN. It is valued at £260,000. The end date for the contract is 19th April 2019.

Two years prison for developer who defrauded £50,000 from flood victims on Huntington Road

A property developer who fraudulently took almost £50,000 from victims of the 2015 floods has been sentenced to 24 months imprisonment at York Crown Court yesterday (7 August 2018).

Owen Danter, aged 40 of 78 Munstead Way, Welton Brough, East Yorkshire, was the sole director of OTD Development Ltd before he voluntarily liquidated the company on 20 April 2017.

He was sentenced to 24 months imprisonment in relation to the 12 charges of Consumer Protection from Unfair Trading for which he had previously pleaded guilty on 19 June 2018.

The charges related to building work by the defendants at two neighbouring addresses on Huntington Road, which both suffered extensive flooding in December 2015.

Both properties had to be vacated by the owners due to the extent of the flood damage.

In June 2016, Mr Danter was employed to carry out the required repairs at both addresses, and by agreement, some additional building work.

At both properties goods were paid for but not supplied. At one property Mr Danter issued nine invoices with a total value of £35,063.82 and to the other he issued four invoices with a total value of £14,483.

On four occasions Mr Danter requested payment be made into a different bank account, because he claimed, hiis bank account had been hacked. He provided alternative bank account details which were his mother’s. The bank confirmed there was no such hacking incident.

By late February 2017, the work was not finished, despite completion dates of November 2016 and December 2016 being previously given, leaving both properties uninhabitable.

In December 2016, Mr Danter disappeared for several days, claiming to have suffered exhaustion and a breakdown, but returned to work.

In February 2017, Mr Danter left the addresses for good, claiming he had suffered a complete breakdown. Between June 2016 and February 2017 both consumers were invoiced and paid for goods and services which did not materialise.

When Mr Danter was challenged about it he gave a variety of reasons – that the articles had been ordered, or that the articles had been paid for or that the articles had been delivered and were in his storage facility.

At interview with Trading Standards officers, Mr Danter admitted his management of the company was poor and that he had taken on too much work and had been involved with four other neighbouring properties. He also explained he had been suffering from depression and was dependent on medication.

Cllr Nigel Ayre, executive member responsible for Trading Standards, said: “Deliberately taking people’s money and not carrying out the work would have a significant impact on most people. But to knowingly inflict that on residents who were in a vulnerable situation following the 2015 floods is far worse. This prosecution shows that we will do our utmost to protect residents from unscrupulous traders.

“Anyone wanting to report poor quality work or unfair trading practices should call the Consumer Helpline on 0345 4040 506.”

HHJudge Hickey told the court: “The deception period was 28 August 2016 to 10 February 2017. The victim personal statements and photos of dilapidation make sober viewing.”

Flooding in York – Update report publised

A further report on plans to deal with flooding in York will be discussed at a Council meeting next week.

Funding has been allocated to the Environment Agency (EA) following the floods in 2015 to renew existing and provide new flood defences across the city, £17m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the City.

Following the development and publication of the York Five Year Plan (https://www.gov.uk/government/publications/york-5-year-flood-plan) the EA have developed the Defra Strategic Outline Business Case and financial approvals have been sought and obtained from Defra.

The report does not provide an update on issues connected with Hob Moor back

click to read

Good work by York Council as Hob Moor access restored

Anyone for a shower?

There are still too many blocked drainage gullies in parts of York. This mornings rain demonstrated the scale of the problem with flooding at the bottom of Hamilton Drive East a particular hazard. There were similar if less spectacular problems on Nigel Grove and Foxwood Lane. All have been reported for attention

Footpath resurfacing delayed but gullies being cleaned in Foxwood

The footpath resurfacing works on Bellhouse Way are currently running about one week behind schedule. Affected frontagers have been advised of the new timetable

Good progress was made yesterday by the gulley cleaner operating in the Foxwood area. Good to see the Council getting ready for winter after the recent problems experienced in parts of the City with surface water.

Flooding in York – where to find information

The government produces maps which show which streets in the City are subject to surface water flooding risks.

Of course, as we saw this morning, other areas can be vulnerable if the capacity of drains is exceeded (and/or they are blocked).

You can access the information here: https://flood-warning-information.service.gov.uk/long-term-flood-risk

Real time flooding maps can be found via this link https://flood-warning-information.service.gov.uk/map

Real time river level gauges can be found here http://www.gaugemap.co.uk/#!Map

The York Council’s surface water management plan can be downloaded from this link http://www.york.gov.uk/download/downloads/id/11055/surface_water_management_plan.pdf

Flooding support deadline set to be 31 May 2017

Floods cost City £3.3 million

The deadline for York residents and businesses to apply for up to £5,000 flooding support is set to be agreed for 31 May 2017.

The national flood resilience grant has helped a wide range of homes and businesses prepare for future flood events, which follows the devastating floods in December 2015.

To-date the council has received 200 applications for support and approved funding for £758,000.

The Council and other authorities were criticised for a slow reaction following the floods on Boxing Day 2015. It was several weeks before financial help was made available through the Flood Disaster fund.and other initiatives.

Anyone who hasn’t yet asked for financial support can still do so.

The application form for the grant is available to complete online at www.york.gov.uk/FloodResilienceGrants .
(more…)