Flooding report – February 2020 wettest on record

£4.9 million cost for pumping station to protect Fordlands Road area.

It cost the City of York council £180,000 to respond to and recover from the floods which took place in the City in February.  This was the wettest February on record, with the most flood warnings issued in any one day across England. Rainfall fell on already saturated ground increasing the impacts.

The Council will consider a report on the problem at a meeting next week.

There is some debate about the apparently conflicting advice issued by local agencies and the information included on government river gauge web sites.

Generally flood defences held well although there were issues in the Fulford/Fordlands Road/Germany Beck area. A separate report on flood prevention plans for that area can be read by clicking here.

The preferred option would include the construction of a £4.9 million pumping station. If funding for the project can be found the work could start on construction next summer.

The meeting will also consider the latest Environment Agency report on its flood prevention works programme

Environment Agency Work Programme 2020

York flood prevention update

The Council will receive an update report on the progress with flood prevention works at a meeting taking place on 13th January 2020.

Flooding in late December 2015 followed an intense period of rainfall across November and December due to the impacts of Storms Desmond and Eva. Record river levels were observed in many river catchments across the north of England. More than 4000 homes and 2000 businesses flooded across Yorkshire with 453 properties and 174 businesses flooded in York

Funding was allocated to the Environment Agency (EA) following the floods to renew existing and provide new flood defences across the city, £28m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the city.

The Yorkshire Future Flood Resilience Pathfinder project led by City of York Council has recruited three Flood Resilience Project Officers who are in the early stages of the development of a range of demonstration and awareness materials that will be used to build flood resilience across Yorkshire.

Flood defence plans criticised by amenity body

The Friends of Rawcliffe Meadows (FRM) are objecting to a plan to raise and extend flood barriers on the river Ouse near Rawcliffe.

Rawcliffe Meadows

They say “FRM believe the Environmental Statement is fundamentally flawed and must be comprehensively revised to give an honest and comprehensive account of the likely destruction of and damage to SSSI grassland”.

They go on to say, “There will be adverse impacts on the Cornfield Nature Reserve which are of regional or at least district-wide significance”.

The comments are revealed in a report to next weeks planning committee which is being recommended to approve the Environment Agency proposals .

The report says, “The application is for works to repair and extend the Clifton Ings barrier bank. This is one of the projects within the agencies flood alleviation scheme (FAS) to reduce flood risk throughout the city. £45 million has been allocated to the EA which will upgrade defences in 19 areas (referred to as flood cells).

The objective of the FAS is to protect against the 1 in 100 year flood (1% AEP) plus climate change and where this cannot be achieved then deliver the maximum level of protection in each cell within the context of existing flood risk and considering other environmental, social and cultural aspects.

The purpose of the barrier bank is to reduce flooding from rivers (fluvial flooding) to the Clifton / Rawcliffe area.

However, during the floods in 2000, water from the river outflanked the flood defences, spilled onto Shipton Road and flooded over 100 homes. The flood basin at Blue Beck also exceeded its capacity in 2000. In these instances, the Environment Agency had to provide temporary pumps to reduce flooding upstream on Blue Beck.

The barrier bank was constructed in 1980. It is of earth fill construction and is up to 4.5m high. The embankments on both sides of the River Ouse currently have issues with stability created by high pressure in the banks when the reservoir empties. This has meant that the drawdown rate for the reservoir has had to be reduced from 1,360mm/day to 300mm/day in order to reduce the risk of failure. This reduction in the drawdown rate significantly impacts on the operation and effectiveness of the reservoir as a flood defence, particularly for any consecutive flood events.

Clifton Ings provides a flood storage reservoir on the eastern side of the River Ouse close to Rawcliffe Park and Ride and the sports clubs Clifton Alliance and York. When not flooded, the northern section of Clifton Ings is used for grazing and the southern section is used as open land by the public. A Sustrans cycle route runs through this area.

During high flow events it has a flood capacity of 2,300,000 m3. It is owned and maintained by the Environment Agency.

The Planning Committee is meeting on Thursday at 4:30pm. The meeting will also consider a separate proposal to create a temporary access route into the site.

Site Plans

York flood prevention update due to be discussed next week

Another update on the work being undertaken to prevent flooding in the York area is being considered on 3rd December.

The report has been produced by the Environment Agency.

Details are also provided on the alleviation plans for the Clementhorpe part of the City.

Regular updates have been provided since the flooding in late December 2015 which followed an intense period of rainfall across November and December due to the impacts of Storms Desmond and Eva.

Record river levels were observed in many river catchments across the north of England. More  than 4000 homes and 2000 businesses flooded across Yorkshire with 453 properties and 174 businesses flooded in York.

Funding has been allocated to the Environment Agency (EA) following the floods to renew existing and provide new flood defences across the city, £17m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the city

Click to read full Clementhore update reprt

Click to read full report

Flooding in York – Update report publised

A further report on plans to deal with flooding in York will be discussed at a Council meeting next week.

Funding has been allocated to the Environment Agency (EA) following the floods in 2015 to renew existing and provide new flood defences across the city, £17m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the City.

Following the development and publication of the York Five Year Plan (https://www.gov.uk/government/publications/york-5-year-flood-plan) the EA have developed the Defra Strategic Outline Business Case and financial approvals have been sought and obtained from Defra.

The report does not provide an update on issues connected with Hob Moor back

click to read

York flooding – more details emerge of £45 million action plan

A meeting on 4th September will, receive an update report on plans to tackle flooding problems in York.

In late December 2015 followed an intense period of rainfall across November and December due to the impacts of Storms Desmond and Eva, record river levels were observed in many river catchments across the north of England.

More than 4000 homes and 2000 businesses flooded across Yorkshire with 453 properties and 174 businesses flooded in York.

Funding was  allocated to the Environment Agency (EA) following the floods to renew existing and provide new flood defences across the City.

£17m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the city

The Environment Agency has produced an update of its 91 point action list, as well as a briefing leaflet (see below).

The decision meeting is open to the public and takes place at West Offices on Monday 4th September starting at 5:30pm

Cycle hub set to become Environment Agency floods showroom

The Environment Agency say they want to establish a permanent exhibition of flood defence works at the former cycle repair workshop in Wellington Row.

They say that the show room would be open “2 or 3” days a week

They have submitted a “change of use” planning application

The showroom would be located only metres away from a key flood defence gate that is closed when the Ouse threatens to overtop its banks