Lowfields – new homes not ready for occupation until next year

This Lowfields site will include 140 mixed tenure homes of which 56 will be affordable homes. The contractor has been on site since December 2019 and the Council says that it is “progressing well” with significant progress on “infrastructure work along with substructures”.

However the first 34 homes are now not due to be completed until early in 2021.

The Council decided to develop the site itself at a meeting held in July 2018

It later formed a company called Shape homes and said it would recruit staff to work with it. The latest financial report suggest that this had not progressed by the end of the financial year with over £1.2 million of the available budget slipping into the current year.

The Council also failed to invest £1.9 million of the budget that it set aside for the repair and modernisation of existing homes.

Football pitches

Meanwhile the football pitch project on Sim Balk Lane has stalled. The pitches were nominally supposed to replace those lost at Lowfields as a result of development, albeit they are 3 miles away. The land near London Bridge became waterlogged over the winter and is only now beginning to grass over.This image has an empty alt attribute; its file name is New-football-pitches-Sim-Balk-Lane-4-4th-Aug-2019-858x1024.jpg

The biggest problem though is the expensive “pavilion” which incorporates changing rooms.

A report to a meeting being held today says, “The construction of the pavilion / changing rooms has been put on hold due to the Covid-19 restrictions and it is not known when the work will be able to restart. The final procurement for the access road has also been put on hold”.

We wish that project well, but would have preferred to see some of the £850,000 cost (to taxpayers) invested in outdoor sports/leisure facilities in the Westfield area.

Huge £1.8 million overspend by Council on James House project

The conversion of James House from offices to 57 self-contained apartments for temporary homeless accommodation was completed on 14th April 2020, fifteen months behind schedule.

The Council says, “For homeless households the self-contained apartments will offer safe, secure and comfortable accommodation before permanent housing can be found for them. James House was open to residents in June 2020”.

The Council now admits that, as well as being 15 months behind schedule, the final costs are currently £1.782m above the agreed budget of £12.4m.

The council says that they have appointed independent experts to review the programming, delay, and quantity surveying aspects of the project.

Latest waste service update from York Council – Wednesday 22 July

We were unable to collect household waste from Kingsway West in Westfield due to access issues. We’ll attempt to collect this household waste on Thursday 23 July, access permitting. Please present your containers for collection by 7.00am.

We were unable to collect recycling from parts of Heworth due to vehicle issues. We’ll collect this recycling on Thursday 23 July. Please present your containers for collection by 7.00am.

We were unable to collect garden waste from parts of Heworth and parts of Acomb due to vehicle issues. We’ll collect this garden waste on the evening of Wednesday 22 July, or onThursday 23 July. Please leave your containers out for collection.

We were able to collect all outstanding waste from Tuesday 21 July.

Waste collection update – Chapelfields affected

After a few good days, when most collections were completed on schedule, vehicle unreliability resulted in delays yesterday according to the Council. They report;

Latest waste service update Tuesday 21 July

All household waste collections have been made.

We were unable to collect recycling waste from Chapelfields and parts of Bishopthorpe due to vehicle breakdowns. We’ll return for this waste on the evening of Tuesday 21 July. Please leave your containers out for collection.

We were unable to collect garden waste from parts of ChapelfieldsAskham Lane and Tang Hall due to vehicle breakdowns.

We’ll return to Chapelfields and Askham Lane on the evening of Tuesday 21 July. Please leave your containers out for collection.

We’ll return to Tang Hall on Wednesday 22 July. Please present your containers for collection by 7am.

We have collected all the outstanding recycling and garden waste from Monday 20 July and Friday 17 July.

Ascot Way disabled centre to open “in October”

Disabled centre on Ascot Way

The Council has changed its forecast completion date for the Centre of Excellence for Disabled Children which is currently being built on Ascot Way. They originally forecast an (unlikely) opening date of June. They have now revised this to October.

The Council says that the facility “will provide short breaks for young people with disabilities in a purpose built facility and also expand the service support offer in the community and assist in reducing the need for out of authority placements by providing much more flexible provision in the city

Lincoln Court

Work on upgrading the adjacent Lincoln Court sheltered accommodation units had stalled during the Coronavirus lock-down. No opening date has been given for reoccupation of the building although this may be influenced by the continuing work on the adjacent site. The refurbishment involves the creation of 15 new fully wheelchair accessible properties and 20 fully refurbished apartments.

We are still waiting to hear when work on the replacement for the all weather play area (MUGA) will start!

Latest planning applications for the Westfield Ward

Below are the latest planning applications received by the York Council for the Westfield ward.

Full details can be found by clicking the application reference

—-

Hutchison 3G Telecommunications Equipment Bellhouse Way York

Erection of 19 metre monopole supporting 6 no. antennas with a wrap around equipment cabinet at the base of the column, installation of 3 no. new equipment cabinets and ancillary development (next to grass verge, adjacent to Community centre, Bellhouse Way)

Ref. No: 20/01183/TCMAS 

—-

28 Rosemary Road York YO24 3FN

Erection of detached dwelling to the rear of 76 Tudor Road

Ref. No: 20/01060/FUL 

——

Representations can be made in favour of, or in objection to, any application via the Planning online web site.  http://planningaccess.york.gov.uk/online-applications/

The Council now no longer routinely consults neighbours by letter when an application is received

Children’s playgrounds all now open in Westfield

Children’s playground in the Westfield area have all now been reopened. Some are displaying “best practice” signs outlining health restrictions. Judging by the numbers in the Acomb Green play area this has proved to be very popular with children (and probably parents).

Acomb Green
Cornlands
Dickson Park
Foxwood Lane
Grange Lane

Planning application for Self build house at Lowfield

A planning application for the first 3 bed “self build” house has now been submitted to the Council. The unit is located to the rear of 76 Tudor Road. Details can be found by clicking the link below https://planningaccess.york.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=QC4PUISJFV100

The Council have now also started to market the houses being built there although it is likely to be some time before they are available for occupation, Click

Anger as Clarke Telecoms refuse to reconsider 5G mast blight

Planning application for 19 metre high Bellhouse Way 5G mast submitted

Despite a hostile response from local residents and Councillors to the informal soundings taken about their huge telecoms mast plan for a site near the Community Centre, Clarke Telecom have now submitted a formal planning application. Click here

Height comparisons and site plan

 Ironically, it comes on the day that the government announced that the mast user, the Chinese company Huawei, would be barred from involvement with the 5G roll out in the UK. Sources say this will put back the 5G timetable by between 2 and 3 years.

A 19 metre high mast in the middle of a residential area (twice the size of the existing mast) would tower over nearby trees, buildings and even lampposts. The ugly equipment antenna  would not be shrouded.

The new equipment cabinets would further obstruct the footpath outside the community centre and would exacerbate problems with anti-social behaviour and trespass.

By far the best option would be for any mast to be located on the Thanet Road Sports area. A site off Foxwood Lane could be found which would have less impact on either peoples homes or leisure buildings.  Existing masts on Thanet Road and Bellhouse Way could then be rationalised to one location which would avoid existing problems with sight lines being blocked for vehicle drivers.

Should this not be possible, then an alternative location, on the opposite side of the road from the Community Centre, would be preferable. This site takes the form of an inset which is currently occupied by cycle hoops (which could be moved into the park).

Suggested alternative location if the mast has to be on Bellhouse Way

Clarke Telecom representatives have offered a series of largely bogus reasons why this site could not be used. An area equivalent to the requirement for the cabinets and pole base has been marked out by the Residents Association. This demonstrates that the proposal could be accommodated with minimal intrusion into the park. If necessary, the railings could be realigned. Any affected trees could be replaced elsewhere in the park.

It is even more important these days that public footpaths be kept clear of clutter as we need to allow plenty of space for “social distancing”. This would mean removing the grass verge if the Community Centre site were approved.

Problems have occurred over the years with youths and criminals climbing onto the cabinets to gain entry to the adjacent car park, centre, and private houses beyond.

Any new mast which may be deemed as essential should be placed next the park where the natural vegetation would help to screen the unsightly utility boxes.

The current proposal represents a visually unacceptable blight on a residential area and should be rejected by the York Council.

Residents wishing to object to the proposal can do so either “on line” through the planning web site https://planningaccess.york.gov.uk/online-applications/ or by Email to planning.comments@york.gov.uk quoting reference 20/01183/TCMAS