Work gets underway to create new cycle/pedestrian bridge in the North of York

Works will get underway from next week to construct a new cycle/pedestrian bridge over the York to Scarborough railway line in Haxby.

Cycle track

This will complete a new safe off-road shared cycle and pedestrian route along the A1237 outer ring road, between the Haxby Road roundabout and the B1363 Wigginton Road roundabout, connecting over 15,000 people living in this area of York.

The contractor PBS Construction (North East) Ltdwill fabricate the main bridge structure off-site, and then plans to lift it into place over the weekend of 15/16 November.

The works were originally planned to commence in 2013, but have been rescheduled to accommodate an alternative design to address ground condition problems, and to meet Network Rail’s requirements to enable contractors to have access to and work close to the railway line.

Works to complete the approach cycle paths will start soon after in late November as well as the installation of a new Toucan crossing on Haxby Road. The new path is planned to become fully operational in early 2015.

Unfortunately cracks have appeared in the section of the cycle track west of the railway line which was completed last year. These appear to be due to the dry summer causing ground movement in some isolated areas.

The council is currently assessing its options to address this problem, which may involve relaying some areas of the path surfacing and filling/sealing the cracks.

Neil Ferris, Assistant Director for Transport, Highways and Fleet, said: “This is one of the largest investments in York’s cycling infrastructure since the introduction of the Orbital Cycle Route in 2011 and will invest £925,000 from the government funded i-Travel, and Local Transport Plan (LTP) funding.

“We’d like to thank those living and working nearby for their patience throughout the period of the works and for the unforeseen delays that we’ve experienced. We are looking to find a solution to address the current issues that will be both long lasting and cost effective.  In the meantime we have put up signs that say the footpath is closed to deter people using it in the unfinished state, and while the overall route is not available.

“We would urge parents not to allow their children to walk or cycle along this path until the full route is open.”

The measures also include links with Haxby Road near to the roundabout, as well as approach ramps on the existing embankments to the new bridge and an additional crossing point on Wigginton Road to safely connect with Clifton Moor.

In addition to main bridge works, and the construction of the link paths, the council is also planting a new hedge alongside the A1237, next to the new fence line that has been established as part of the scheme. This planting is expected to happen in October/November.

The council intends to also amend the Public Right of Way across an adjacent field just west of the railway, with a view to improving access and reducing potential conflict between pedestrians, cyclists, and agricultural vehicles in this area.

The provision of an off-road route/safe link opens up access (sustainably, via cycling and/or walking) between Haxby, Strensall, Huntington, Earswick, New Earswick and to the retail, leisure and employment destination of Clifton Moor as well as students attending Joseph Rowntree School.

The new cycle route will be the flagship scheme of City of York Council’s four-year i-Travel initiative, made possible by £4.6 million of government funding which the council successfully bid for in 2011.

The Clifton Moor retail, leisure and employment area attracts around 6-million visitors every year and supports 6,000 employees.

In addition to the new cycle route, the council has also addressed the lack of good pedestrian and cycle routes within the Clifton Moor retail / leisure area itself by investing almost £100,000 of government funding in 2013 on new pedestrian and cycle crossing facilities, cycle lanes, and measures to slow traffic speeds, by introducing easier and safer access for pedestrians and cyclists.

To find out more about the new cycle route and bridge visit: www.york.gov.uk/haxbytocliftonmoor

Hamilton Drive resurfacing delayed until 27th October

Road closure - click to enlarge

Road closure – click to enlarge

Road to be closed

City of York Council is to reconstruct Hamilton Drive carriageway starting on the 27th October 2014.

This is 3 weeks later than originally planned

The works are programmed to take one week to complete, working Monday to Friday between 09.30am and 5.00pm. The area affected is shown on the plan.

The Council says “To carry out the works safely, the road closure will be in place from 09:30 to 17:00 Monday to Friday, with some accommodation works taking place outside of these times.

Due to the nature of the works and the deep excavations taking place, it will not always be possible for residents to gain vehicular access to their properties. In these circumstances residents should be prepared to use alternative parking.

Pedestrian access will be available at all times. Cyclists will have to dismount and use the footways when travelling through the affected areas”.

Success for Hamilton Drive West resurfacing campaign

Repair work starts on 6th October

Hamilton Drive - sections to be resurfaced click

Hamilton Drive – sections to be resurfaced click

Following many months of complaining, the Council has agreed to resurface the section of Hamilton Drive West between Green Lane and Lady Hamilton Gardens.

Originally this section had not been scheduled for resurfacing before 2016.

However Andrew Waller pointed out that the surface had deteriorated to the point where one more severe winter would see he road crumble and repair costs spiral..

The ruts represent a hazard for both pedestrians and cyclists while motorists have complained about the ever deepening potholes.

The Mattison Way to Campbell Avenue section of the road will also receive attention

 

 

 

 

 

Walmgate road-works anger

road works

Sleepless nights as work overruns evening deadline

For the second night running, resurfacing works near Walmgate Bar have extended beyond the 11:00pm deadline.

Local residents have complained that they had been given no notice of the changes to working hours which were announced 2 weeks ago.

Earlier in the week a fractured water main was blamed for congestion but the Council have yet to explain the cause of the latest delays.

The Council originally said that works would be restricted to the period between the hours of 6.30pm and 11.00pm.

The works are scheduled to be finished by 19th September.

For details any emergency works on Walmgateafter 11pm @YorkshireWater @YWHelp can advise

— City of York Council (@CityofYork) September 12, 2014

Traffic congestion on Walmgate/Foss Islands Road/Barbican Road/Lawrence Street from Monday

Carriageway Resurfacing Works

City of York Council is to resurface the carriageway at the junction of Walmgate/Foss Islands Road/Barbican Road and Lawrence Street starting on the 8th September 2014.

The works are programmed to take approximately 2 weeks in total to complete, working weeknights only between the hours of 6.30pm and 11.00pm.

In order to carry out these works safely, the use of a temporary road closure will be necessary whilst works are taking place. A signed diversion route will be in operation for local and through traffic whilst the works are ongoing. Outside of working hours, the road will be open to traffic as normal.

York potholes being filled in

DSCF3194 York-20131223-01260

The Councils pothole team are currently operating in the Westfield area.

We hope that they will fill in the many potholes that have developed over the last couple of years.

It is important that residents continue to report issues as they arise.

A damaged road surface is more vulnerable to frost damage and would cost much more to resurface in the long term

The work forms part of a £300,000 pothole programme funded by the Coalition government.

It is separate from the resurfacing programme which takes longer to complete each year. This is the programme which was drastically cut by Labour when  they took office.

The resurfacing programme has so far reached Huntsman’s Walk where the footpaths have now been repaired.

Road repairs

Vesper Drive and York Road

York oad work

York oad work

The annual safety inspection of Vesper Drive was carried out yesterday. Temporary repairs will be carried to maintain the carriageway safe for the public to use until the full resurfacing scheme is completed later this financial year

Meanwhile work continues to move the Controller (new location) for the pedestrian crossing on York Road/Manor Drive.

The controller box is being moved to a more suitable location away from vehicle’s accidentally reversing into it