Further road closures as work continues on Stonebow, Fossgate and Pavement

As work nears an end on Stonebow, Pavement and Fossgate residents are being reminded of overnight road closures needed to finalise the project.

These include full overnight closures (Monday to Friday 8.30pm to 5am only) on:

  • Pavement – between 25 March and 5 April
  • Fossgate – between 25 March and 12 April and,
  • Stonebow (closed in Pavement direction) between 1 and 5 April

In addition, between 25 to 29 March (over-night only) traffic will flow in the opposite direction on Colliergate so that work can be completed at the junction of Whipmawhopmagate. This may impact people driving in the city, particularly taxi drivers.

It is anticipated that the day time closures of Stonebow, Pavement and Fossgate will be completed on time by 29 March.

The road works are part of a £1.1million investment by the City of York Council to make major improvements to Stonebow, Fossgate and Pavement in York’s city centre. The works will improve the street’s appearance and character, create a more pedestrian-friendly environment and improve access for pedestrians and cyclists, which will attract more visitors to the area.

Tony Clarke, Head of Transport at City of York Council said, “We are nearing the end of a 14 week programme of improvements in the area. These closures have always been in the plans to finalise the work but hopefully taking place overnight will cause the minimum upheaval and disturbance possible.

“We know that the closures have caused delays and disruption for some and we would like to thank residents, businesses and commuters for their patience and assure everyone that we are working hard to have all routes fully reopened by 12 April.”