York Council investment programme slips

A Council report shows an out-turn of £35.751m on the Council capital investment budget compared to an approved budget of £52.428, an overall variation of £16.677m.

Community stadium start slips

The biggest slippage (£3.5 million) was on the York Central project although there were also delays in other areas including school maintenance, housing construction, the Glen Lodge extension, waste disposal, IT development and upgrades to buses.

The report shows that expenditure on the Community Stadium has also slipped again with the bulk of the work now expected in 2018/19. In total, the Council will spend £36 million on this project although this figure does not include the substantial sums spent to date or the (privately funded) commercial elements of the project.

The report goes on to say;

Mansion House cost up by £150,000

  • that the Mansion House restoration scheme has an outturn position of £1.031m in 2016/17, requiring re-profiling of £515k of funds from 2017/18 into 2016/17. The work is now expected to be completed in August 2017.  The report goes on to say that “as the works contract has progressed a number of areas of additional work have been identified as necessary to safeguard the future of the Mansion House, these essential restoration works will cost an additional £150”.
  • the Tenants Choice programme saw 120 properties have their kitchens, bathrooms and wiring updated through the year. This is significantly lower than the 220 properties that were planned. This is due to problems with tenants refusing works, delays due to damp problems and delays with kitchen deliveries. The scheme under spent by £416k in 2016/17
  • the proposed developments at Newbury Avenue and Chaloners Road have also been delayed. The development now proposed is for 5-6 bungalows and “will be submitted for planning approval in July”. The development of homes at Chaloners Road was postponed when the developer withdrew from the contract. A revised scheme will be submitted for planning approval in late summer 2017
A summary of the Councils £1/4 billion investment plans can be found below

Plans for new development on Tadcaster Road by Wilberforce Homes

Local residents are invited to attend a drop-in session to have their say on proposals by the Wilberforce Trust to build 30 flats for its tenants on land it owns to the north of The Grove, off Tadcaster Road.

The proposals, which include a social/community hub for tenants and offices for the charity, will be on display at the Sunflower Centre at St Leonard’s Hospice on Thursday 6th July from 4.30pm to 8pm. A Wilberforce Trust leaflet (copied below) is being delivered to local homes to publicise the drop-in session.


The Wilberforce Trust is a York-based charity that provides specialist housing and support for people with visual impairments, sensory impairments and other disabilities. Its website can be viewed at www.wilberforcetrust.org.uk

In the most recent draft Local Plan, this piece of land had been provisionally allocated for residential extra care facilities in association with the Wilberforce Trust.