Poppleton Bar – delays continue as Council responds to Freedom of Information request

At the last Council meeting Councillors were told that all work on the Poppleton Bar Park and Ride project would be completed by the end of July.

No end to Poppleton Bar works

No end to Poppleton Bar works

However there is still a considerable amount of work outstanding with periodic impacts on congestion levels in the area.

While the final May deadline for conclusion of the whole Access York contract is long past, it is unclear why there are continuing delays at Poppleton (other than the obvious one that the contractors are simply not fully resourcing their contract obligations).

Cycle tunnel in use but no lane marking on paths

Cycle tunnel in use but no lane marking on paths

Councillor Ann Reid is now pressing for answers and some have emerged as responses to Freedom of Information requests

One (click to download)  confirmed that the whole Access York project – of which the Poppleton works form part – was due to be completed by 23rd May.

Details of the road closure orders have also been published on the Council’s web site

Meanwhile, the permanent traffic signals at the A59 junction with the Park and Ride access road are now in place, but the following work is still outstanding

  1. Considerable surfacing and landscaping work
  2. White lining (e.g. on the cycle path exit from the A1237 pedestrian/cycle tunnel. (If this is intended to be a shared cycle/[pedestrian space then it does not seem to comply with the specification agreed with the Blind and Partially Sighted Association)
24 hour lighting on new roundabout

24 hour lighting on new roundabout

Yesterday (Thursday) the street lights in the area were permanently lit. Taken with the decision to exclude the provision of on-site electricity generation from the project, this does seem to fly in the face of the Councils environmental policies?

Drivers now want a realistic completion date for the project.

Residents would also like to be reassured that there are penalty clauses in the contract which will be invoked to compensate the Council, taxpayers and drivers for the inconvenience and additional expense that they have suffered over the last few months.

More traffic light failures

Press 17th Oct traffic lights

As we reported 6 months ago the reliability of traffic signals in York has plummeted in the last couple of years.

The Council have not yet published a root cause analysis of the failures which – today – again brought traffic chaos to the City centre.

Signals on the Fishergate loop were responsible for the problems.

Its about time the Council got to the bottom of these problems.

Gridlock forces Lendal Bridge and Coppergate re-opening

Burst water main in York today

Burst water main in York today

As had been forecast, gridlock on the inner ring road forced the Council today to reopen Lendal Bridge and Coppergate to general traffic.

However it wasn’t a major accident on the trunk road network or very bad weather that prompted the Council to remove the restrictions.

A burst water main in the Piccadilly area was to blame.

The Council agreed to waive access restrictions on both Coppergate and Lendal Bridge.

However their decision came at lunch time and was too late to help the hundreds of drivers that had been caught up in the jams during the previous 2 hours.

The traffic restrictions are likely to be re-imposed tomorrow.