Community Stadium – unanswered questions to get public airing

Call for business case and Yearsley guarantee

Stadium Project

Liberal Democrat councillors are calling for guarantees over the future of Yearsley Pool and more information on the financial plan for York’s Community Stadium.

The Lib Dems have ‘called-in’ the Labour Cabinet’s decision last week to approve plans for York’s Community Stadium.

The decision will now be re-considered at a cross-party scrutiny meeting on Friday 26th September.

Under the latest plans for the stadium and leisure complex at Huntington, total costs for the scheme rise to £37m and the Council will borrow an extra £4m towards financing the project.

The plans have been attacked by users of Yearsley Pool, which could close under the proposals, and York City Knights, whose chairman says the scheme would leave the club “70% worse off”.
(more…)

Stadium will cost Council Taxpayers £1 million a year.

Huntington project administration costs hit £6 million

More details of the changes to the Huntington Community Stadium project have emerged. The papers reveal the administration and project team costs for the project have increased from £3.5 million to £6 million.Stadium Project

The Council will borrow a total of £8 million, meaning that local taxpayers will have to find £720,000 a year in debt charges. In addition the Council will contribute £323,000 towards the annual running costs.

The report talks about a developer paying £12 million for land on which to construct 6000 square metres of retail and commercial space.

This space would be used for

  • Retail units totalling 4245 sq m
  • Two restaurants totalling 110 sq m
  • A digital cinema with bar totalling 1652 sq m

There are numerous risks identified for the project.

The land was originally acquired by the Ryedale Council for leisure purposes. There may be at least a chance that the original owners will seek a share of any enhanced value resulting from commercial development.

Equally the inclusion of – yet more – out of City centre retail development will be controversial.

This is the issue most likely to delay the granting of planning permission and could result in the application being “called in” by central government. In turn, this would impact on the target start (April 2015) and completion (July 2016) dates.

The Council don’t rule out a Judicial Review – a process initiated by opponents of change and  which added, in the last decade, nearly 2 years to the timetable for  modernising the Barbican auditorium.

A 15 month construction commissioning timetable looks highly ambitious anyway.

Less obvious risks may arise. Not least the ubiquitous Great Crested Newts who mounted a strong resistance to being evicted from the neighbouring John Lewis site.

The report confirms that

GLL will be responsible for the overall management of the site and the direct management of the Community Hub, leisure facilities and associated assets. This will be controlled by an overarching lease and management contract for a 13 year period with a 5 year extension option.

As part of the procurement process, GLL have appointed York City Football Club (YCFC) as a sub-contractor to operate the stadium area. YCFC will work with CGC (York Racecourse hospitality company).

The proposal will involve changes to the existing parking and access arrangements. This will see the re-routing of Kathryn Avenue around the stadium, creating a pedestrian only and fan zone, strengthening links with the Vanguard retail scheme

The report also says that “All community hub tenants will enter into lease agreements with CYC for the use of the facilities. All leases have been set at appropriate commercial rates”.

The report includes a table showing how costs have increased over the last couple of years

Component Approved March 2012(£Ms) Approved Nov 2012(£Ms) Proposed Sept 2014(£Ms)
Community Stadium 14.2 14.8 16
Leisure Complex 0 0 12
External works 1.5 1.45 3
NSLC sub total 15.7 15.25 31
Other facilities / Project costs & contingencies 3.5 3.95 6
Total 19.2 19.2 37
Commercial Development Costs (externally funded) 10
Gross Total Cost 19.2 19.2 47

Increased cost of Community Stadium is bad news for taxpayers

Future of Waterworld and Yearsley pools under threat

08-27-2014-08-48-27-555

Labour are circulating a glossy brochure ahead of the publication of a report on the future of leisure provision in the City.  Private briefings to staff and media have raised serious issues about the future of swimming and other facilities in the City.

The project will now cost £37 million in total with Greenwich Leisure (who have operated Waterworld for the last 3 years) taking on responsibility for all major sporting and swimming facilities in the City.

Greenwich Leisure are a CIC although the level of local York engagement – if any – in their management decisions and structure has yet to be announced.

Community Stadium

The project will cost taxpayers £8 million more than originally budgeted. It had been expected that a 6000 seater stadium and replacement athletics track could be built for the £12 million contribution from the John Lewis development.  The Council would have contributed only the value of the Huntington Stadium site (conservatively assessed as £4.1 million). The Football Foundation would have put in the £2 million that it had loaned against the value of a redeveloped Bootham Crescent.

Later Labour said that they would spend the £4 million contingency included in the Councils budget for the project. This had been included as a potential loan which would be repaid from stadium income.

Now Labour are stating that they will borrow an additional £4 million bringing the taxpayers contribution up to £8 million in total, with the stadium capacity increased to 8000 (it costs roughly £1 million for every additional bank of 1000 seats).

It is highly unlikely that such an additional burden could be passed on to the Football and Rugby clubs with details of their rental agreements not having yet been revealed.

At a time when the campaign forsafe standing” – backed by the Liberal Democrats is gaining momentum – local fans will be bemused that the design does not appear to provide for rail seats (although this modification could still be made)

Council taxpayers will be responsible for the debt repayment charges on the amount borrowed which will be around £600,000 a year. It is far from clear where this money will come from although some additional “commercial elements” have been designed into the scheme.

Given the controversy about out of city centre shopping, this raises doubts about how long the planning process might take and with it the ability of any contractor to meet a July 2016 opening date.

 Waterworld

Waterworld and its associated gym will close in December.

A new pool and gym will be designed into the stadium. However it will be more conventional than Waterworld with only a small “fun” pool included.

Waterworld is only 20 years old and with that kind of life one wonders how durable such facilities now are? (The Barbican pool lasted for 40 years, Yearsley is over 100 years old)

Since the opening of the Sports Village on Hull Road, the Council has met national standards for the provision of swimming pools.  There is insufficient demand to pay for an additional swimming pool (which is why Labour quietly dropped their plans for a city centre pool).

Yearsley Pool

Under Labours plans, the opening of the new pool at Huntington will mean the end of the Council subsidy (around £250k pa) for the Yearsley pool. The unique 50 yard pool has fought off two previous attempts by Labour to close it although ironically in early 2011 – following a £1 million refit undertaken by the then LibDem controlled Council – Labour invented a bogus  “closure” rumour and campaigned against something that was not going to happen.  A new boiler was fitted at the pool meaning that the steam heat supply from the Nestle site could not attract disproportionately high charges.

Yearsley Pool

Yearsley Pool

Labour have now performed a 180 degree policy about turn.

The only chance for the pool would be for users to acquire the site and run it independently as a community asset. However it is highly unlikely that that increased admission charges could make up the financial deficit – more so as it would have to complete with three other modern pools in the City not to mention those at several independent sports clubs, hotels and schools.

Its only hope would be for Nestle to relent and allow a profitable gym to be added although this might involve them losing some car parking space.

Energise

The management of Energise – the sports facility on Cornlands Road – seems less threatened by the take over plans.

The centre is very popular and no doubt Greenwich Leisure will want to keep it that way.  However standardisation of charges and facilities, together with focusing some types of provision at just one site, may prove to be a challenge in the future.

No guarantees are being offered on admission charges although heavy competition from the private sector may help to keep them down.

What next?

The Stadium project is running over two years behind timetable. The publication of a report, for decision by the Councils Cabinet on 9th September, is belated but welcome.

Residents will be looking very carefully at the business plan for the new facility as the Council – which will remain the freeholder – does not want to risk having to step in to recover a failing project a few years down the line (as happened in Huddersfield a few years ago).

The changes to the retail component of the project do raise planning issues that may take some time to resolve, jeopardising the construction start date..

Whether a July 2016 opening date is realistic remains to be seen.

Official: Community Stadium completion date –“July 2016” – Cllr Crisp

The responsible Councillor has confirmed an opening date for the new community stadium at Huntington as July 2016 – just a few weeks before the start of the football season.

She confirmed that work will start on site in March 2015.

As the Council has yet to appoint a contractor much less get detailed planning permission – residents, taxpayers and football supporters will be looking with interest at the next stadium report which is due to be discussed on  2nd September

Huntington Stadium April 2014

 

York Community Stadium – 2 year delay confirmed

2016 opening date now in doubt

The latest timetable for the construction of the new community stadium at Huntington confirms that it is running over  2 years behind the timetable set by the new Labour council when it was elected in 2011.

York stadium-Aerial

The previous LibDem administration had identified a way of funding the £14 million project and it had been expected that construction would take place alongside the new John Lewis store which opened on 10th April 2014. That part of the project had been delayed by 6 months following the discovery of Great Crested Newts on the site.

The Councils timetable showed a completion date of  June 2014 just early enough to allow the football club to move from Bootham Crescent this year and well before the start of the rugby season.

Council papers now reveal that final tender papers are only due to be received this month and that the Labour Cabinet is therefore unlikely to award a contract before its meeting on 2nd September 2014.

It could then be 4 months before a planning application is submitted.  Although the principle of the stadium use has already been established, there is likely to be a 3 month delay before the proposal reaches the Planning committee in March.

March 2015 (just 2 months before the next Council elections) was the absolute firm date given by the present Council Leader for a start on site – but that new looks increasingly unlikely.

Construction work will take two years, so there is now doubt about whether the stadium will be ready for the start of the 2016 football season.

The delays also impact on the running of other major leisure facilities in the City – such as Energise – which the Council wants to include in an all encompassing management contract.

NB A question on the progress being made with the leisure contracts was tabled at the last Council meeting but no response from the responsible Cabinet member has yet been published.

Community Stadium opening date – York Council to hear latest fantasy league predictions

Huntington Stadium April 2014
Leisure chief Cllr Sonja Crisp will be asked to give a firm opening date for the new Community Stadium at Huntington when the Council meets on Thursday.

Funding for the stadium (£12m) was agreed in 2010 and confirmed when planning permission for the new Monks Cross development was granted in 2011.

That development – which includes the John Lewis store -was finished and opened several months ago.

The Council has been very slow to start work on an alternative athletics facility having dithered over the precise location for the track on the York University campus.

Only an immediate start on the stadium in the autumn (when the athletics season comes to an end) would give some hope that it could be in use for the 2016/17 football stadium (the Football League frowns on Clubs that try to change homes mid season)

"I've still got a job in football. I'm building the Huntington Stadium" click for full interview

“I’ve still got a job in football. I’m building the Huntington Stadium” click for full interview

But the Stadium  has yet  to receive detailed planning permission and Cllr Crisp has been unable to even decide who will manage the stadium.

Cllr Ian Cuthbertson has now tabled the following question for the meeting next week,

“What is the Cabinet Member’s deadline for starting work on the ground at the new Community Stadium at Huntington and what is her current best estimate of its opening date?”

In April, Council Leader James Alexander tweeted to give an absolute guarantee that “construction work on the Stadium would start by March 2015”

Most stadia take at least 18 months to build.

Waterworld sinking?

Energise Pool It looks like the delays on the Community Stadium project are now beginning to hit other parts of the City’s leisure services.

The Councils Labour Cabinet are set to hand an additional £450,000 to the contractors running Waterworld next year to keep it going.

The delay in letting a comprehensive contract – to run all building based leisure facilities in the City – means that Energise will be asked to find an additional £20,000 in income while it looks like the Yearsley Pool will be required to fund savings of £100,000!

Users will be eagerly awaiting news of how these economies will be achieved.

Increased admission charges have already been announced

York Community Stadium size shock

The Councils Cabinet is to consider an update on the much delayed Community Stadium at its meeting on 7th January.

The Council is seeking an operator who will design, build, operate and maintain the stadium. They will also manage and maintain the Councils other Leisure facilities such as the successful Energise sports centre on Cornlands Road.

Given the Council somewhat varied track record on Leisure centre management (the Barbican was costing taxpayers £800,000 a year until it was privatised), the Council is probably correct to seek a professional organisation to manage the Stadium.

Athletics layout - Heslington West click for original

Athletics layout – Heslington West click for original

Discussions with 2 preferred bidders are expected to continue until March. Their plans will be kept secret until later in the year.

The Council says that “All submissions were able to meet the basic minimum criteria set of 6,000 capacity all-seat stadium, community hub within the financial parameters of the project”

However designing the stadium so that it can be expanded in capacity later is described as having “major cost implications” and it seems that the initial capacity may be increased to over 6000 with “some terraced standing space”.

That is likely to please many football supporters but it would be at the expense of later expansion capability.

It seem likely now that a stadium with a capacity of 7000 will be provided but with the capability of expansion to 10,000 only if Championship (or Super League) promotion is achieved.

The report confirms that the costs of running the stadium will be covered “through a mix of the rentals from the sports clubs, the community hub tenants and other commercial income streams brought forward by each bidder. This will include full maintenance and lifecycle costs as part of a 13 year operational contract”.

The Council are now talking about opening the stadium in spring 2016.

Final Tenders

May 2014

Planning   & Project Agreement Live

January   2015

Work starts on site

February   2015

Stadium Opens

February / March 2016

The £2 million athletics facility at Heslington West is expected to be opened in September 2014. A copy of the design specification for the athletics facility can be viewed here.

The Cabinet report includes a list of the risk factors that must be addressed. Not least amongst these is the need to meet the requirements of the Football Foundation who loaned York City £2 million in 2005.

Knavesmire sports pavilion slips 12 months….Community Stadium update

New pavilion design

New pavilion design

The ambitious plans to provide a replacement pavilion on the little Knavesmire for the Hamilton Panthers football team looks like being delayed.

The York Council has set aside £350,000 to part fund the £600,000 project. But it seems that funding from Sport England has been delayed.

The project which will see a new clubhouse and changing rooms built on the site of an old ROC World War II building was given planning permission in 2012.

At that time it was hoped that the new facility would be available for use in early 2014, but this now seems unlikely

————-

The Council is also saying that the new Community Stadium – which will be built on the site of the existing Huntington Stadium – will cost £1.85 million this year.

The total cost is now put at £18.6 million

It is unclear how the council intends to recover it’s investment (now thought to be around £4 million) or whether it includes the capitalised salaries of those who are working on the project.

It is understood that formal bids for the construction of the stadium will be considered in January, with the hope that construction will be completed in 2016.

The project is running 2 years behind schedule.

Blow for Sports Village hopes. Community Stadium to be delayed?

The Council has announced that it will no longer be funding an athletics track at the Sports Village on Hull Road.

The facility was to have opened this year.

The proposal to establish a sports village – which also includes swimming pools, 3G football pitches, a fitness suite, a outdoor cycling circuit and spa facilities – was agreed over 3 years ago and most of the facilities are now in use.

Athletics stadium Sept 2013

However, the provision of a new £2 million athletics stadium was to be the final jewel in the crown.

The intention had been to maximise the use of shared facilities such as the refreshment area, physiotherapy, spa and changing rooms.

Now the Council has decided to refurbish the University of York running track on Heslington Lane which is nearly 2 miles away from the Sports Village. The Heslington/Fulford area already suffers from traffic and parking issues

The implications for the running costs of both facilities remain unclear as does the financial commitment of the Council to the whole Community Stadium project.

A spokesperson for the Labour run council has claimed that the new site will be “cheaper”.

However, the athletes are claiming that the Council has agreed to subsidise the York Athletic Club for “5 years”.

Who has agreed such a subsidy, with what restrictions and for how much remains a mystery?

Behind closed doors logo

This major change in policy was taken at another behind closed doors meeting, so taxpayers are being kept in the dark

Moving the athletics track from the Huntington Stadium was an essential precursor to work on the new stadium starting.

It now seems that athletes will leave Huntington in late 2014 prior to occupying the refurbished University track in 2015.

Completion of the Community Stadium has already been put back to 2016 and further delays cannot be ruled out.