Ascot Way building works update

The cost of the Centre of Excellence for Disabled Children, currently being constructed on Ascot Way, has increased by £1.2 million.

Part of the additional funding is coming from the NHS

The “current timeline for the centre is for the main build to be completed by January 2020 with opening scheduled for May 2020”.

A council report says that, during quarter 1 within the Lincoln Court Scheme, the work to relocate all Lincoln Court tenants into alternative accommodation was completed successfully, this has then allowed Sewell’s to take possession of the site, undertake site set up and begin enabling works.

This has included a full invasive asbestos survey and works to build an access road and car parking for sub-contractors accessed via the Hob Moor primary academy site.

All the remaining window replacement works have been completed in this quarter as has the demolition of the single storey extension in preparation for works to begin for the new build extension.

The Council says that “the Centre of Excellence and Lincoln Court project teams have worked together to communicate with residents neighbouring the site and also to keep Ward Councillors updated on project progress. £750k budget has been transferred from 2019/20 into 2020/21”

There is still no update provided on  the promised replacement children’s games area will be provided