Traffic signals to be upgraded at Monks Cross junction

New traffic signals will be installed at the pedestrian crossing/road junction in Monks Cross this month, ahead of the new York Stadium and Leisure Complex opening later this year.

Outdated traffic signals at the junction of Kathryn Avenue and Jockey Lane at Monks Cross are set to be replaced by City of York Council.

Works will start on Monday 29 April and are estimated to take around four weeks to complete. The hours of working will be 7.30am – 5.30pm, Monday to Friday and 9am – 3pm on Saturdays.

The new technology being installed will help to ease congestion in the area and enable the new systems to link direct to the council’s Traffic and Control Centre, so that Network Monitoring Officers can manage the flow of traffic better in busy periods.

As with any construction work, there is likely to be a certain amount of disruption. Residents are assured that everything reasonably possible will be done to keep this to a minimum.

During the works it is anticipated that all bus services will operate as normal, however there will be delays when travelling through the junction. 

Temporary crossing points will be available at all times during the works to ensure that all pedestrian crossings that are currently available are maintained.  Traffic marshals will be on site between 7am and 7pm, seven days a week to assist with pedestrians crossing the road.

Residents are urged to plan ahead, allow more time for journeys on these routes and to consider alternatives and to use public transport where possible.

Bus services will be operating as normal for the majority of the works but passengers are requested to visit www.itravelyork.info/ for more information.

For information regarding the scheme during the works visit: www.york.gov.uk/KathrynAve